A quiet unmarked road curves beside grassy acreage and mature live oaks and palms in a leafy Florida neighborhood.

Malabar's 2023 Road List Is Down to Benjamin Road, and the Next Round Already Has Names

Benjamin Road is 18 feet of asphalt running west of Corey Road, and about half of it sits in Grant-Valkaria. In 2023 an engineering survey found edge cracking along its narrow lane. The same survey noted that several dirt roads in both towns reach Corey Road by way of Benjamin. Out of the ten roads Malabar ranked as its worst three and a half years ago, it is the only one that hasn't been rebuilt.

The other nine are finished. A newly scored list of ten streets now sits behind Benjamin, and it looks very different from the 2023 one. The first round fixed main roads that were close to failing. The next round is mostly short neighborhood streets with modest wear. Benjamin is the road between those two phases, and it's the one where more than paving is involved.

The 2023 list was a rescue job

On April 3, 2023, the Town Council accepted a town-wide pavement evaluation from Engineering Design & Construction Inc. The town manager's summary says it "revealed severe network failures." Eight of the ten highest-priority segments had less than five years of service life left, which meant full reconstruction was the only repair that would work. Council appointed Mayor Steve Rivet to work with town staff on a phased plan.

The council's 2023 ranking named Briar Creek Boulevard, Weber Road, Rocky Point Road, Corey Road, Benjamin Road, Coral Way, Huggins Drive, Coquina Terrace, Hollow Brook Lane and Booth Road. If you've driven through Malabar in the past three years, you've probably been on at least one of them in the middle of construction. According to the November 16 Town Council agenda, the work went in this order:

  1. August 2023: Weber Road
  2. October 2024: Rocky Point Road, Coral Way, Huggins Drive, Coquina Terrace
  3. November 2024: Corey Road
  4. February 2025: Briar Creek Boulevard, Booth Road, Hollow Brook Lane

The town says the rebuilt segments now score 0.10 or lower on its maintenance scale, where a lower number means less wear.

How the town paid for it

The program drew on a $3.5 million long-term infrastructure loan and $340,345.82 in federal ARPA funds. All of the ARPA money went to Weber Road. That's $3,840,345.82 in total. The November agenda puts spending to date at $2,315,461.44 across completed repaving phases, localized structural repairs and safety striping, which leaves $1,524,884.38 unencumbered.

So the program's work so far has used about 60 percent of the money, and roughly 40 percent is still in the account. The agenda earmarks that balance for Benjamin Road's construction, engineering and inspection, including widening. It says the balance also covers future repaving priorities with no new borrowing.

Why Benjamin went last

The other nine segments were Malabar's to fix on its own schedule. Benjamin needs widening, it runs through people's front yards, and the town doesn't control the whole road.

In 2023 the engineers recommended full-depth reclamation and shoulder stabilization. That means grinding up the old pavement and rebuilding the base, and then firming up the road edges. A fresh layer of asphalt alone wouldn't cover it.

The town line made it harder. Grant-Valkaria's November 13, 2024 council minutes record Malabar's request to repave and widen Benjamin Road and its question about sharing costs, since half the road is in Grant-Valkaria. Grant-Valkaria's council agreed to have its own town engineer prepare an estimate so it could consider cost sharing.

Design work started this summer. Citizen Portal reported that on July 20, 2026, the Malabar Town Council voted 4-0 to hire Bowman Consulting Group for preliminary roadway plans at an estimated $60,936. Council Member Marisa Acquaviva made the motion and Council Member Mary Hofmeister seconded it. According to the same report, the plans have to deal with driveways, utility poles and stormwater. Construction cost estimates and any cost sharing between the towns come after the plans are done.

The $60,936 pays for the drawings only. Construction is a separate cost. The November 16 Town Council agenda scheduled a preliminary engineering presentation and design review for Benjamin Road. It describes the project as "fully transitioned out of scoping." For anyone who uses Benjamin to get between Corey Road and the dirt roads on the Grant-Valkaria side, that review is the first real look at what the widened road will be.

The next ten

The same agenda item asked council to accept an updated set of pavement distress scores from October 2026 and post them on the town website. Those scores produce a new top-ten backlog. Benjamin is still on it, in third place.

Rank Road Length Width Oct 2026 score Town's note
1 Jordan Blvd 1,010 ft 70 ft 6.25 Very wide footprint; heavy staging for industrial-zoned uses
2 Riverview Drive 780 ft 20 ft 3.25 Immediate candidate for the next overlay package
3 Benjamin Road 3,375 ft 18 ft 2.00 Final 2023 carryover, in design with Bowman
4 Blanche Street 1,060 ft 20 ft 2.00 High-density local segment
5 First Lane 240 ft 20 ft 2.00 Short local segment
6 Florence Street 1,060 ft 20 ft 2.00 Same wear as Blanche; bid them together
7 Century Oak Circle 1,260 ft 20 ft 1.75 Degradation approaching; monitor
8 Gilmore Street 1,280 ft 20 ft 1.75 Wear tied to commercial uses at the Post Office; serves a neighborhood off State Road 514
9 Glatter Road 2,890 ft 18 ft 1.75 Over half a mile; local-traffic-only posting and narrow two-lane use under evaluation
10 W Railroad Avenue 1,830 ft 20 ft 1.75 Rounds out the top ten

Most of the list is ordinary neighborhood streets. Seven of the ten are 20 feet wide. First Lane is only 240 feet long. Together the ten roads add up to about 14,785 feet, or roughly 2.8 miles, and Benjamin alone accounts for close to a quarter of that.

The scores are lower than the 2023 situation suggested, too. Only Jordan Boulevard and Riverview Drive score above 3. The other eight fall between 1.75 and 2.00. In 2023, eight of the top ten were within five years of failing. This list describes wear the town can get ahead of. The agenda's own wording is about scheduling: Riverview is an "immediate" overlay candidate, Blanche and Florence should go out to bid together, and Century Oak Circle is on a watch list.

What the scores show about waiting

The town's score summary shows each backlog road's 2023 adjusted score next to its October 2026 maintenance score. Jordan Boulevard rose from 6.00 to 6.25 and Riverview Drive from 3.00 to 3.25, while Benjamin, Blanche, First Lane and Florence climbed from 1.75 to 2.00 and Century Oak Circle and Gilmore Street from 1.50 to 1.75.

Each of those roads moved up by the same quarter point over about three and a half years. The rebuilt roads dropped to 0.10 or below in the same period. Benjamin already had the town's attention in 2023, and it's still slowly getting worse while the design and the conversation with Grant-Valkaria move forward.

Where each road sits for daily driving

If your routine runs on State Road 514, Gilmore Street is the road on the list you're most likely to use. The town ties its wear to commercial uses at the Post Office, and notes that it also serves a neighborhood off 514. Jordan Boulevard tops the list, but it's a 70-foot-wide collector serving industrial-zoned uses, and the town expects the job to need heavy staging. Glatter Road's note goes beyond pavement. At more than half a mile, it's flagged for a look at local-traffic-only posting and its narrow two-lane use.

People on the west side of town also have a stake in Benjamin's design, because it runs straight into Grant-Valkaria. If you follow that town's public projects, our recent post on Grant's season at First Street covers another piece of road work moving through the planning process, and the Grant-Valkaria page collects what's going on across the line.

Parks and Recreation Board meetings are on the town calendar for November 18 and December 16, both from 5 to 6 p.m. Road items go to the Town Council, and the council agenda packets are posted in the Town of Malabar Agenda Center. That's where the Benjamin Road plans and the updated scores will show up.

At Team 321 Launch, we keep track of projects like Benjamin Road because the condition of a street matters every day to the people who live on it. If you'd like to know what the October 2026 scores mean for your block in Malabar, or anywhere on the Malabar side of the county, contact us and we'll go through the town's documents with you.

Work With Us

Whether you’re buying, selling, or investing, we bring the experience, persistence, and strategic guidance to help you move forward with confidence.

Follow Us on Instagram